VDG Victory on Leonard Project Update: May 2022



We are currently in month 7 of our 18-month construction schedule. There's a lot to see in this month's update!


  • We are completing the last section of our foundation walls.

  • Consumers Energy has decided they want to bury the power lines that run along the south-side of our property.

  • We're almost through the de-watering challenges, and once completed all of the 'unknowns' in the ground will be behind us.

  • Steel arrives next week to frame the first floor.

  • Tower two is under construction—this is where our elevator will be located and also indicates the highest point of our building.

  • We have a handshake agreement with a potential retail tenant and are working toward a letter-of-intent. We can't announce who or what it is yet, but we believe it will be a huge amenity for our residents and the neighborhood.


Thanks for your investment in Victory on Leonard, and thanks for helping us build much-needed new housing in Grand Rapids!