We are currently in month 5 of our 18-month construction schedule. February was a slow month for us due to weather conditions, although we've still managed to make a lot of progress.
We did experience some water conditions in the soil once we moved from the perimeter into the center area. We've had to remove the bad soil and purchase gravel fill for compaction purposes.
We're also beginning to form and pour our foundation walls and will continue this process for the next several months. You can look forward to seeing the masonry work begin for our stairwells and elevator shaft very soon. We love it when the steel and concrete start coming out of the ground!