top of page

VDG Victory on Leonard Project Update: June 2023



We are currently in month 20 of our Victory on Leonard 120-unit apartment construction schedule.


• The black metal panel installation is pretty much complete around the exterior of the building


• We've begun laying brick around the building exterior


• We have an elevator! Installation will be complete in the next two weeks


• Gypcrete has been poured on floors A 3&4. Gypcrete is a slurry of concrete and gypsum that allows for fire rating and sound dampening


• Case work and trim has begun. Cabinets will be installed starting Monday

• The model unit will be available for showing starting July 5


• We are still within our original budget. However it does look like we'll be using our entire contingency allowance due to the delays with the city and inspections


• We're on schedule to deliver the units on floors A 3 & 4 by September 1, with residents moving in on September 15


• We have some interest on the retail space, but no signed LOI's yet. Brad did talk with a bakery that could be a good fit for our space

bottom of page